Main Street in Somerton will see temporary closures for the next three weeks, city officials have announced.
This follows repaving work that closed down a portion of the major thoroughfare for months earlier this year. Although it came at a slower time for local businesses, some business owners were not happy with the detour they said kept customers away.
Somerton city officials said they want residents, business owners and workers and motorists to know a revised schedule for Main Street/U.S. Highway 95 between Somerton Avenue and the Regional Center for Border Health clinic.
This is part of the Main Street Redevelopment Project city leaders say will beautify the area around Somerton City Hall.
A new schedule has been announced due to a delay in materials. Crews were scheduled to complete concrete pours on Monday for archway columns and wayfinding columns.
This Thursday through Nov. 25 crews are scheduled to install all archway steel. Main Street will reopen on Nov. 25 once steel installation is complete. City officials say that will allow traffic to move though Main Street during the Thanksgiving holiday weekend.
On Nov. 30 (Cyber Monday) crews will begin to install the final three-inch layer of asphalt, signage and striping. Main Street will reopen once striping and signage are complete by Dec. 5, with plenty of time before the annual Somerton Tamale Festival on Dec. 19.